23/10/2015 – Second Floor Frames & Roof
Upper floor frames completed, lower floor roof framing done and part of upper floor roof finished.
22/10/2015 – Bracing, Joists & Safety Rails
Temp Bracing, Bracing Ply, Floor Joists completed and Safety Rails installed.
21/10/2015 Lower Frames and Joists Completed
Progress by end of the day.. All lower floor frames have been erected and most of the floor joists have been installed.
21/10/2015 – Lower Frames Going Up!
Frames are going UP!! Carpenters are hoping to have joists and upper floor completed by Friday I sort of gave them the incentive of a slab or two if they … Continue reading
14/10/2015 & 16/10/2015 – Moisture Barrier & Steel
Not much progress for the last couple of days. 14/10/2015 – Moisture barrier fitted to slab edge. 16/10/2015 – Steel delivered.
13/10/2015 – Fill Spread Around Slab
Fill removed from trenches and site scrape used to spread back around slab to divert rain away from slab.
12/10/2015 – SLAB POURED!!!
WOOHOO.. Powering On!!! We now have a SLAB!!!!
10/10/2015 – Slab boxed up, pods and mesh installed.
And considering the shit weather yesterday I didn’t think we would see anything else done till next week BUT.. we decided to go past this afternoon and check anyway and…. … Continue reading
08/10/2015 – Mesh & Rio
No progress today. Only mesh and rio delivered ready for next week. Hope the weather is good!!!
07/10/2015 – Trenching, Plumbing and Meterbox
More progress today!! Electrician is out there now fitting the meter box and connecting the 3 phase power, plumbers are doing the trenches and plumbing.